Project Details Razi 3rd Ammonia Razi 3rd Ammonia Status: Completed Registration Date 2008/11/04 Update Date 2008/11/13 Goals 1- usage & hyrogenized gases which exist in the area 2- expanding down stream industries Schedule Project Start Date : 8/5/2002 12:00:00 AM Project End Date : 3/4/2005 12:00:00 AM Description Group : 3 Agreement Date : 8/5/2002FeedstockFeedAmountSourceMethane50 mf3/dPetrochemical Special Economic zoneImpure gases contaning hydrogen17t/hPetrochemical Special Economic zoneInvestment: $213.5mn Licensor &Basic Engineering: Ammonia Casale,BASF Detail Engineering & procurement:PIDEC Value of excavation/earth filing: 12,000 m3 Value of concrete work: 16,000m3 Weight of steel structure: 1,200 tonnes Weight of equipment : 14,857 tonnes Piping:170,000 inch-diam Cable work: 260 km Piling:45km Engineering work:365,500 man/hour Erection &Construction : Petro Sanat ,Pishgam sanat,Palar &Gil Foam Actual physical progress (as of 22 oct 2003):21/2% Manpower during operation :480