Group : 3
Budget No : 23-167
Agreement Date : 6/15/2001
Control Unit : Consortium of Sazeh & Snamprogetti
Investment:$19.5mn
License &Basic Engineering:Norsk Hydro& Snamprogetti
Detail Engineering & procurement :Consortium of Sazeh &Snamprogetti
Erection &Construction: Consortium of Sazeh & Snamprogetti
Major local manufacturers: Tarvig Felez
Volume of concrete works (m3): 1,300
Weight of steell structure (tons): 1,000
Weight of equipment (Tons): 850
Piping (inches-dia): 21,750
Cable works (km): 50
Engineering works (man/hour): 140,000
Erection &Construction(man/hour):1,500,000
Actual physical progress (as of 6 sep 2003):100%