Project Details

REVAMPING OF UREA PLANT NO.2

REVAMPING OF UREA PLANT NO.2
: Completed
2008/11/04
2015/03/03
Goals
-increasing of product of plant up 1800 t/d of urea -perform of hazop study -Increasing the quality of produet -Revamp of unit
Schedule
Project Start Date : 7/11/2002 12:00:00 AM
Basic Contractor
TECNIMONT
Description

Group : 3
 Budget No : 23-026
 Agreement Date :  7/11/2002
Control Unit :  STAMICARBON
 
-         Changing of CO2 compressor

-         Changing of cooling tower and circulating pump

-         Changing of control system

-         Adding of one HP Ammonia pump

-         Adding of one HP carbamate pump

-         Changing of pre evaporator

-         Changing of LP carbamate condenser

-         Adding of one urea melt pump

-         Changing of some tray of reactor

-     Modification of ejectors of evaporating section

-         Basic Engineering activities like updating of P&IP,

Equipment layouts, interlock description have been completed

-         Detailed Engineering activities like issue of P&ID for engineering, material requisition for long delivery and critical item completed

-         Procurement action for compressor and HP pumps are in advanced stage

-         Procurement action for cooling tower, cooling water pump, melt urea pump and hydrogen converter has commenced

Summery of project:

-         Revamping of urea plant No.2

·        Engineering services

1-    Basic Engineering

2-    Detail Engineering

·        Procurement services

-         Refurbishment of existing equipment

جزئیات طرح یا پروژه - طرح 2

REVAMPING OF UREA PLANT NO.2
Project Introduction

Group : 3
 Budget No : 23-026
 Agreement Date :  7/11/2002
Control Unit :  STAMICARBON
 
-         Changing of CO2 compressor

-         Changing of cooling tower and circulating pump

-         Changing of control system

-         Adding of one HP Ammonia pump

-         Adding of one HP carbamate pump

-         Changing of pre evaporator

-         Changing of LP carbamate condenser

-         Adding of one urea melt pump

-         Changing of some tray of reactor

-     Modification of ejectors of evaporating section

-         Basic Engineering activities like updating of P&IP,

Equipment layouts, interlock description have been completed

-         Detailed Engineering activities like issue of P&ID for engineering, material requisition for long delivery and critical item completed

-         Procurement action for compressor and HP pumps are in advanced stage

-         Procurement action for cooling tower, cooling water pump, melt urea pump and hydrogen converter has commenced

Summery of project:

-         Revamping of urea plant No.2

·        Engineering services

1-    Basic Engineering

2-    Detail Engineering

·        Procurement services

-         Refurbishment of existing equipment