Group : 3
Budget No : 23-026
Agreement Date : 7/11/2002
Control Unit : STAMICARBON
- Changing of CO2 compressor
- Changing of cooling tower and circulating pump
- Changing of control system
- Adding of one HP Ammonia pump
- Adding of one HP carbamate pump
- Changing of pre evaporator
- Changing of LP carbamate condenser
- Adding of one urea melt pump
- Changing of some tray of reactor
- Modification of ejectors of evaporating section
- Basic Engineering activities like updating of P&IP,
Equipment layouts, interlock description have been completed
- Detailed Engineering activities like issue of P&ID for engineering, material requisition for long delivery and critical item completed
- Procurement action for compressor and HP pumps are in advanced stage
- Procurement action for cooling tower, cooling water pump, melt urea pump and hydrogen converter has commenced
Summery of project:
- Revamping of urea plant No.2
· Engineering services
1- Basic Engineering
2- Detail Engineering
· Procurement services
- Refurbishment of existing equipment