Finding the reasons, remedy the deficiencies and optimum use of furnace tubes with standard life time
Schedule
Commencement Date : 10/21/2001 Duration : 12Months
Basic Contractor
METALLURGY DEPARTMENT-ENGINEERING FACULTY OF SHIRAZ UNIVERSITY
Description

Contract Code: 80/053


 Since, the primary reformer furnace tubs are exposed on high temperature and high pressure so, high resistance of tubs against the creep, corrosion and thermal fatigue phenomena is an important factor that is effective in the production continuity, and since the approximate lifetime of used tubs in this condition is estimated about one hundred and thousand hours and unfortunately, this used tubs are involved premature failure and they have failure in a time less than 1/10 of their useful life. So this project is designed and performed for investigating the premature failure reasons and improving the condition for optimizing the systems in order to use the tubs in estimated useful life

Address: Imam Khomeini Port, Postal Agency 113, PO Box 161

Phone :061-523-41517-8
Fax:061-522-62096-7 
 
Telephones : 021-88945001