Project Details

Feasibility study for liquefaction and solidification of CO2 gas
Feasibility study for liquefaction and solidification of CO2 gas
: Completed
2008/11/04
2008/11/04
Goals
Economical feasibility study for liquefaction of CO2 gas for later projects in order to provide primary material for consumer industries
Schedule
Commencement Date : 7/25/1998 Duration : 2Months
Executive Actions
RESEARCHING AND ECONOMICAL EVALUATION OF THE PLAN
Basic Contractor
Abadan petroleum faculty – Dr. Behrooz Roozbehani
Description

Contract Code 77/088


 Produced CO2 gas in ammonia unit is approximately 1.5 ton corresponding to each production ton and about 18 ton per hour imports in environment which can be used in painting, molding, armory and beveraging industries and fire fighting. This project investigates liquefaction and solidification of CO2 gas in two phases. The first phase is about economical evaluation of plan, Razi complex agreements about its continuity and capitalizing, and technical study and process designing will be in the next project.

Address: Imam Khomeini Port, Postal Agency 113, PO Box 161

Phone :061-523-41517-8
Fax:061-522-62096-7 
 
Telephones : 021-88945001
customer relation management : 06152262111